November 10 thru December 22, 2015 | Letters of Interest submitted by Interested Parties to be included on Priority List to purchase a unit based upon seniority. Building under construction.
|
After December 22, 2015 | Interested Parties may submit a Letter of Interest but will be placed at the end of the Priority List with no consideration of priority based upon seniority.
|
December 22, 2015 thru January 29, 2016 | Vista will establish a Priority List of interested parties/buyers by entrance date of the student/member (seniority) to establish the order in which a potential buyer may select a unit.
|
January 29, 2016 | Announcement of Priority List of interested parties/buyers.
|
February thru April 2016 | Developers contact interested parties in order of priority to select a unit. Model one and two bedroom units will be available no later than April 2016 for viewing. Purchasers will execute purchase and sale agreements.
|
June thru July 2016 (est.) | Completion of construction and Certificate of Occupancy. Closing on units and operation of facility by Vista and Settlers Landing Association, Inc. is initiated. |